Construction updates
April 19 to 25, 2026
• No thru traffic on 1st Street
• No thru traffic on Center Lane from 1st Street to 2nd Street
• Traffic control in place
• “No flush” notices will be distributed in the area
April 26 to May 3, 3036
• 1st Street will open to traffic
• Centre Lane will be closed between 1st and 3rd Street
• 2nd Street will be temporarily closed
Read the two-week look ahead:
Background
Last spring, staff presented an update to Council on sewer and wastewater treatment plant projects to be funded through $7.5 million federal / provincial Investing in Canada Infrastructure Program (ICIP), and funding was confirmed in December 2025. Projects will replace sewer infrastructure damaged during the 2021 fire and improve capacity and infrastructure as Lytton rebuilds.
The Village provides sewer services for properties in the Village of Lytton and Lytton First Nation’s IR 17 and IR 18.
Project overview
Starting this spring and continuing for 4 to 6 months, the West of Main Street Sewer Replacement Project will include the following:
- Sewer main replacement in the following areas:
- Center Lane from 1st Street to 6th Street, 6th Street to Main Street, and Main Street from 6th to 7th Street
- West Lane from 1st Street to the Community Hub site on Fraser Street
2. Sewer connections in the following areas:
- On 1st Street from Main Street to Center Lane
- On 2nd Street from West Lane to Center Lane
- On 3rd Street from Main Street to Center Lane
- On 4th Street from Fraser Street to Center Lane
3. Associated improvements for storm sewers and water mains
This project will move the Village’s main sewer line, which carries sewage from IR 18 and the north end of the Village, from West Lane to Center Lane. It will also upgrade the watermain on West Lane and the storm sewer mains on Center Lane and 6th Street.